Work has progressed rapidly since our last update, with over 60 units from a total of 90 which make up the temporary school now delivered and installed on our playing field.
These units make up part of the main school building and a separate, a single story building also being built containing our dining hall, kitchen and sports & production hall.
A further delivery of units is due in the next few weeks. Students had a chance to view the temporary school and their classrooms before they left for the summer holidays to help them understand what to expect when they return in September.